Office Design Follow-up Report United Medical Group Limited
- AVA Interior Design & Construction Co. Ltd.
- Mar 28
- 2 min read
We completed a 7,504 square foot office renovation for our client, United Medical Group Limited, using a commercial style design and completed the entire project in approximately 60 days.
We provide each customer with detailed construction progress reports, including weekly site photos and detailed work instructions. Even if you are too busy to visit the construction site, you can still keep track of the construction status at any time through these reports. Our team conducts regular on-site inspections and ensures that all construction details meet your expectations.
Office renovation project preparation stage

Revise the floor plan and readjust the ink lines according to customer requirements

Gypsum board partition materials delivered to the site

Protect cargo in elevator lobbies and rear doors
Week 2
Protect the elevator door entrance and fire door of the office building
Removal of old floor and ceiling in office building elevator lobby
Single-sided plasterboard partitions in all offices are under construction
Install high and low voltage iron troughs in office ceilings
Begin installing soundproofing pads on the gypsum wall partitions in some offices
Week 3
Installing a new air conditioner in an office building
Office reception is under construction
Started to work on the ceiling of the open office staff area
Use cement to seal the floor pipes in the office
Start office computer cable project
Started office basement painting project
Week 4
Sealing of all office room gypsum board ceilings
Completed installation of all office room glass frames
Week 5
Complete the office luminous sign threading
Completed the office reception wallpaper project
Completed installation of glass partitions in office meeting rooms
Start wallpapering your office room
Office room white glass under construction
The office staff area ceiling and corridor louvered ceiling are under construction
Completed the office meeting room wallpaper project
Week 7
Office furniture arrival and installation